Project Details

This greenfield project involved stripping topsoil and constructing a substation pad. This included installing 336 screw piles, 4 breaker pads, 2 transformer pads with Sorbweb oil containment, and constructing the substation access road. Finally, the site was remediated by placing topsoil and grass seeding.

CAP’s Role

CAP was awarded the entire civil scope for this project. We oversaw our earthworks operators, as well as our concrete, civil, oil containment, and screw-piling subcontractors. To ensure open and thorough communication between our subcontractors and the client, we provided daily progress reporting and attended weekly construction meetings.

We procured all materials to construct the substation pad, transformer, and circuit breaker pads. On top of managing third party material testing, we conducted regular quality checks during earthworks, concreting, and screw piling. Our subcontractors consulted with us on every issue encountered. We also managed all quality and safety aspects of the job.

 

Project Statistics

Year Completed: 2014
Our Services: Project Management | Civil Construction | Material Testing | Field Engineering
Project Location: High River, AB

Similar Projects

Marystown Salmon Hatchery
2018 (estimated)
Grieg NL Seafarms Ltd has chosen Marystown, NL to locate a new, state-of-the art, land-based salmon hatchery and growth facility. This facility, when fully
Marystown Water Street East
2017

This roadway project consisted of replacement of the water, sanitary sewer and storm sewer systems, as well as all new pavement along the entire street.

Shakwak Highway Quality & Quantity Control
2012
The Government of Yukon required quality and quantity control services for two warm mix asphalt pavement (WMAP) projects on Shakwak Highway. CAP monitored and
Ross River Road and Drainage Upgrades
2012
Situated on the south bank of the Pelly River, Ross River is a small community in east-central Yukon. Cyclical spring thaws and ice jams caused Pelly River to flood